INFORMATION SHEET

 

BOILER WATER/FEEDWATER TEST AND TREATMENT

Information Sheet Number 62B-231

 

 

INTRODUCTION

 

            The goals of successful boiler water treatment are to prevent scale formation and to minimize corrosion and carryover.  The Chelant boiler water treatment system is a continuous treatment system which minimizes boiler water chemistry fluctuations associated with the old manual test and treatment systems.  Batch treatment chemicals are used to adjust chemical levels for initial treatment and during contamination incidents.  The continuous blowdown system is used to prevent the build up of excessive treatment chemicals and to remove the chelated metals.  These three systems work together to maintain the boiler chemistry levels within parameters.  The term Chelant comes from the Latin for claw or talon and refers to the Chelant system's ability to chemically "grab" boiler water impurities. 

 

REFERENCES

 

            (a)  Boiler Water/Feedwater Test and Treatment NSTM 220 Vol. 2 (Rev. 6)

            (b)  Boilers NSTM Chapter 221

           

INFORMATION

 


A.                 Shipboard Water Cycle

 

1.         Terminology

 

a.         Although the shipboard water cycle is continuous, different terminology is used to describe the water at different points.  These distinctions are necessary because water quality standards vary throughout the system.  The following terms identify the water at various points.

 

b.         Distillate is the evaporated water that is discharged from the ship's distilling plant. Water in the shipboard water cycle normally begins as distillate.  This distillate is stored in the reserve feedwater tanks until needed as makeup feedwater.

 

c.         Reserve Feedwater and Makeup Feedwater:  Distillate stored in the feedwater tanks is called reserve feedwater.  The water flowing to the condensate system from the feed tanks is makeup feedwater.  In ships equipped with demineralizers, the water flowing out of the demineralizer to the condensate system is termed demineralized makeup feedwater.

d.         Condensate:  After steam has done work, it is returned to the liquid state by cooling in a condenser.  The condenser is a heat exchanger in which steam, under vacuum, flows over and is condensed on tubes through which seawater flows.  The liquid condensed from steam is called condensate.  Water from other sources (such as makeup feedwater and low pressure drains) is mixed with and becomes part of the condensate.

 

e.         Feedwater:  The term feedwater defines the water contained between the DFT and the boiler.  This water is of special quality, as it has been heated and deaerated in the DFT.

 

f.           Boiler Water:  The deaerated feedwater, as it enters the boiler steam drum, is defined as boiler water.  The term boiler water describes the water in the steam drum, water drum, headers, and generating tubes of the boiler.

 

g.         Freshwater drains:  Steam drains from various steam systems throughout the engineering plant are collected and returned to the system via the freshwater drains.

 

(1)      Steam drains are collected from various steam systems by means of funnel drains with swing check valves installed to prevent backflow of the drains.  This drain collecting system is designed to collect condensate from piping during light-off, securing and casualty situations.

 

(2)      Equipment and steam systems using steam below 150 psig, are designed with a continuous drainage capability.  Some examples of equipment include:  lube oil heaters, saltwater heater drains from distilling plants, and drains from air ejector condensers. 

 

h.         Low pressure drains:  As a great deal of low pressure steam is used for auxiliary functions outside the engineering spaces, as much of the condensed water as possible is recovered and reused.  Some examples of contributors to the LP drain system are:  galley, laundry, ship's water heaters and the scullery.  This is a common source of boiler water contamination.

 

B.                 Goals of Chelant

 

1.         The goals of successful boiler water treatment are to prevent scale formation and to minimize corrosion and carryover.  These conditions can be caused by saltwater or shore water contamination.  Saltwater or shore water contamination will introduce calcium, magnesium, and chloride ions into the feedwater and boiler water systems.

 

2.         Three results of contamination

 

a.         Scale formation:  Calcium and magnesium are the major hardness constituents and the primary sources of scale in boilers and feed system heat exchange equipment. All scale deposits act as insulators and reduce the heat transfer across the particular surface.  Deposits will cause the temperature of the metal to increase until overheating, metal softening, blistering, and failure occur. 

 

b.         Corrosion:  There are basically eight types of corrosion which are found as a result of contamination.

 

(1)      High dissolved oxygen:  causes hematite (red rust)

 

(2)      Ammonia corrosion:  found in copper alloy piping (such as the condensate system).

 

(3)      Chloride stress corrosion:  transgranular cracking will occur where there is stainless steel.

 

(4)      Oxygen pitting:  high levels of dissolved oxygen will result in pitting and scabs will form over the pits.

 

(5)      Caustic stress corrosion:  where there are deposits present, hydroxyl ions will collect and cause corrosion, cratering and gouging of tube metal.

 

(6)      Acid attack:  an excess of hydrogen ions will corrode tube metal which will create a methane gas which will stress the tube and cause it to crack.

 

(7)      Chelant corrosion:  an over treatment of boiler water with EDTA will thin the walls of boiler tubes.

 

(8)      Electrolytic corrosion:  when two dissimilar metals are joined together, and there is an electrolytic solution present (i. e.. boiler water), electrons will move from one metal to another leaving behind a defect in the wall of the tube.

 

(9)      Chloride pitting:  an aggressive ion which deteriorates the walls of boiler tubes.

 

c.         Carryover:  Steam slugs will normally break and release dry steam in the steam drum.  A high concentration of suspended dissolved matter in boiler water will stabilize steam slugs and prevent them from breaking.  This will result in carryover, which enables wet steam and water to impinge on turbine blading,valves and create water hammer which can damage piping and pipe hangers.

 

C.                 Chelant Treatment Chemicals

 

1.         Trisodium EDTA:  one of a class of organic chemicals known as chelating agents or chelants.  EDTA chelates dissolved metals, including the scale formers magnesium and calcium, by surrounding and bonding to the metal at several places.  Thus, magnesium and calcium are prevented from forming scale on the boiler tube surfaces.  Since the chelates remain dissolved, they do not contribute to sludge formation in the boiler.  Chelation is the primary method of removing magnesium and calcium ions from boiler water.  EDTA also generates a magnetite layer, which is a microscopic film formed on the walls of the boiler tubes to help protect the metal from corrosion.

 

2.         Trisodium Phosphate/Disodium Phosphate (TSP/DSP):  the secondary method of removing magnesium and calcium ions from boiler water is through the introduction of phosphates and alkalinity.  If a large amount of contamination causes all of the EDTA to be consumed by magnesium and calcium ions, then the excess ions will form scale.  By having a residual level of phosphates in boiler water, which is kept slightly alkaline, then the excess magnesium and calcium ions will form sludge instead of scale.

 

3.         Hydrazine:  enhances the magnetite layer and acts as an oxygen scavenger.  The DFT cannot remove all of the dissolved oxygen from feedwater.  Hydrazine will consume any oxygen which is not removed in the DFT.

 

D.                 Chelant Boiler Water Control Limits (table 1)

 

BOILER WATER CONTROL LIMITS

A.                  

CONSTITUENT or PROPERTY

 

REQUIREMENTS

 

ALKALINITY

0.100-1.000 epm

 

PHOSPHATE

10-40 ppm

 

CONDUCTIVITY

500 mmho/cm

 

CHLORIDE

1.0 epm

 

 

 

Table 1

 

1.         Alkalinity:  There is a minimum limit for alkalinity in order to prevent acid attack and the formation of scale if EDTA is depleted.  There is a maximum for alkalinity in order to prevent caustic corrosion and carryover of water with the steam.

 

2.         Phosphates:  There is a minimum limit for phosphates in order to provide a level of residual phosphates for the formation of sludge vice scale if EDTA is depleted.  There is a maximum limit in order to prevent carryover of water with the steam.

 

3.         Conductivity:  There is a maximum limit in order to prevent carryover of water with the steam.

4.         Chloride:  There is a maximum limit for dissolved chloride ions in order to prevent the types of corrosion mentioned above.

 

E.         Continuous Treatment System (figure 1)

Figure 1

 

1.         The purpose of the continuous treatment system is to inject EDTA, TSP/DSP, and hydrazine into the DFT.

 

2.         The treatment tank holds 30 gallons of treatment solution which is a mixture of the three chemicals condensate.  Nitrogen is used to mix the chemicals in the tank with the condensate and pressurize the tank in order to force the chemicals into the DFT. The nitrogen pressure on the mixing tank is adjusted between 20 and 60 psig to achieve proper treatment flow.  The required pressure will vary between systems depending on the location of the mixing tank relative to the DFT.

 

3.         There are two alarms associated with the treatment tank.  The five gallon alarm indicates that preparation of fresh treatment solution will be required shortly.  The continuous treatment tank is normally filled when the two gallon alarm sounds, but may be filled when the level is below five gallons if drills or other operations are expected to conflict.  When the treatment level reaches two gallons, a solenoid valve closes, securing the flow of treatment chemicals to the DFT.  The continuous treatment tank shall be refilled  and placed back on line within one hour after the two gallon level alarm sounds, except when it is anticipated that all the boilers in the space will be secured within twenty-four hours.  This will minimize any waste of chemicals.

 

F.         Batch Treatment (see figure 2).  There are two times when batch treatment is done:

Figure 2

1.         Freshly fill and treat (FFT):  Accomplished when initially filling a dry boiler with untreated feedwater.  A standard dosage of chemicals must be added in order to raise the level of alkalinity and phosphates to be within the boiler water control limits and provide EDTA and hydrazine.

 

2.         Casualty control:  a dosage of treatment chemicals is injected when there is a boiler water casualty resulting from seawater or shorewater contamination.  This casualty dose is necessary because the continuous treatment system discharges at a constant rate regardless of any of contamination.

 

Figure 3

G.        Continuous Blowdown System (figure 3)

 

1.         The continuous removal of boiler water is necessary in order to control the level of conductivity caused by the chelated metal ions.  This is accomplished by allowing the continuous flow of boiler water through the blowdown piping, past the boiler sample cooler, to the bilge.

 

2.         A continuous monitor is being installed on all new construction ships and ships already in commission are being retrofitted.  The continuous monitor allows supervisors to monitor the conductivity of the boiler water.

H.        Surface and Scum Blowdowns

 

Figure 4

1.         Surface blowdowns (figure 4):  shall be performed on a steaming boiler as necessary to reduce high levels of alkalinity, phosphates, conductivity, or chloride and to remove light suspended solids.  The surface blowdown pipe is located on the steam drum three inches below the normal water level.  One surface blowdown will remove the top three inches of steam drum water. The surface blowdown procedure will result in approximately a 5% decrease in alkalinity, phosphate, conductivity, and chlorides.  This is the only method for reducing high levels of chloride in a steaming boiler.  Surface blowdowns are required less frequently under chelant treatment due to the use of the continuous blowdown system.  When a surface blow is required, boiler water chemistry limits must first be checked to ensure the boiler chemistry is never reduced below the minimal chemical limits.  For example, scale formation may occur if the boiler is steaming with alkalinity less than .050 epm and acid corrosion will occur if alkalinity is 0 epm. The surface blowdown evolution takes approximately 45 minutes. Throughout the surface blowdown the water level will be controlled in remote manual and the speed of the ship should be maintained steady with little or no change in steam demand.

 

2.         Scum blowdown (figure 4):  A scum blowdown is performed in order to prevent the accumulation of light suspended matter in the steam drum.  A scum blowdown utilizes the surface blowdown piping, but only removes the top one inch of water from the steam drum.  If the boiler has been secured for more than two hours, then a scum blowdown is required following the first boiler water sample that is above the lower alkalinity and phosphate limits after coming on line.  At a minimum, a scum blowdown must be conducted weekly.  When a surface blowdown is performed, that will zero the hours used to calculate the next scum blowdown. The scum blowdown evolution takes approximately 15 minutes and the water level will be controlled in remote manual.   

 

I.          Boiler Lay-ups

 

1.         The method of idle boiler lay-up chosen depends on considerations such as maintenance or repair work scheduled, planned duration of lay up, effectiveness of the lay up method, availability of support for the lay-up method, and boiler recovery time.  With a cold boiler it takes approximately 2-3 hours minimum to light off and bring it to operating pressure.  Lighting off from a steam blanket lay up takes approximately 1½-2  hours minimum to be at operating pressure.  If done faster, could cause damage from thermal shock.  The following is a description of boiler wet lay-up methods and time limitations.

 

a.     The steam blanket lay-up method uses 150 psig steam from the 150 psig desuperheated steam system or shore source steam that meets specifications outlined in NSTM chapter 220 V2.  This provides reasonable protection for the boiler watersides, firesides and superheater but, does not provide protection for the economizer.  This lay-up is applied as soon as residual steam pressure has dropped below steam blanket supply pressure.  The steam keeps the boiler warm and requires no special preparation to get the boiler underway ready.  A steam blanket lay up is limited to thirty days.  At the end of thirty days, the boiler must be placed on a hydrazine wet lay-up or a dry type lay-up if not lighted off.

 

b.     The nitrogen blanket lay up uses one or more compressed nitrogen gas bottles connected to the boiler through a regulator and small piping system.  The regulator is adjusted to maintain 5 psig constant pressure on the boiler to keep oxygen out.  This provides reasonable protection for the boiler watersides and superheater, but does not provide protection for the economizer.  This lay up is applied when residual steam pressure is at or below 5 psig.  Since the boiler is cold, heat should be applied to the firesides to protect them from corrosion.  This lay up requires no special preparation to get the boiler underway ready.  A nitrogen blanket lay up is limited to thirty days.  At the end of thirty days, the boiler must be placed on a hydrazine wet lay-up or a dry type lay-up if not lighted off.

 

c.     The hydrazine/morpholine lay up can be applied at any time by ship's force.  This lay up requires the boiler to be completely filled and all air expelled.  A constant pressure must be maintained with the use of a head tank or pump.  Preparation for light off requires a portion of the hydrazine/morpholine to be drained and properly disposed of in accordance with pollution control NSTM chapter 593.  This lay up also has no time limit.

 

2.         Dry lay up methods are used when boiler watersides are to be opened for long term inspection or repair.  There are two dry lay up methods that can be used and the preliminary procedures are the same for each method.  Dry lay up methods provide reasonable protection for boiler watersides, economizer and firesides provided the boiler is completely dried out after dumping.  Both methods have no time limit.  The following is a description of boiler dry lay up methods.

 

a.         When boiler pressure has dropped to 0 psig dump the boiler completely.  After the boiler is thoroughly drained and opened it must be completely dried out.  Starting from the top of the boiler using low pressure air to blow out all accessible surfaces including all boiler tubes, drums and headers.  Do not contaminate the boiler with wet or oily low pressure air.  Thoroughly inspect all waterside surfaces to ensure they are dry, then apply one of the following lay up methods.

 

b.         The hot air lay up method uses an electric heater and blower to circulate hot air through the boiler watersides and firesides as long as the boiler is idle.  This requires all accesses to be closed with the exception of the hot air entry and exit point.  Special adapters are needed to attach the blower connections to the boiler.

 

c.         The desiccant lay up method uses bags of desiccant to keep the boiler dry.  The amount of desiccant used varies by boiler capacity.  Follow the procedures in Boilers NSTM chapter 221.  The bags are evenly distributed through all boiler drums, headers and the economizer.  A count of bags is made as they enter the boiler and the count is logged in the engineering log when removed.  A desiccant bag inadvertently left in a boiler will cause adverse effects in the boiler water chemistry after light-off.  Humidity cards are placed inside the boiler to indicate when the bags need to be changed.  The boiler is then closed up.  It is recommended to have plexiglass covers made to fit the boiler steam and water drum accesses so that humidity cards can be observed easily.

 

d.         Preparation for light off can be very time consuming depending on boiler integrity and repairs.  Remove the desiccant or hot air blower connections, clean all gasket mating surfaces as required and close the boiler.  Flush the boiler by refilling the economizer and superheater with feed‑quality water and dumping.  Refill the boiler and conduct a hydrostatic test accordance with boilers NSTM chapter 221.

 

J.          Safety 

 

1.         There are a number of safety precautions to be observed when testing or treating boiler water and feedwater. Many of the chemicals employed are either acids or alkalies. All are poisons when ingested. Sampling can be dangerous if procedures are not followed exactly or if equipment is faulty. Immediate medical attention shall be obtained if any chemical is swallowed.

 

a.     Treatment chemicals

 

(1)      A face shield shall be worn when mixing treatment chemicals to prevent contact with alkaline treatment solutions.  A faceshield is worn when treating the boiler because of the possibility of hot feedwater spraying back on the operator should an error or equipment malfunction occur.  A faceshield, goggles, apron, and  plastic or rubber gloves shall be worn when injecting caustic soda, handling hydrazine or morpholine solutions.

 

2.         Obtaining samples

 

a.     Sampling of boiler water or deaerated feedwater can be dangerous because live steam can discharge if instructions are not followed exactly. Coolers can rupture because  of the pressures involved. For boiler water sampling, the cooling water flow must be established prior to opening any valve in the sample line. For dissolved oxygen sampling, pressure in the secured cooling water line must be relieved.

           

b.     A face shield shall be worn when obtaining a deaerated feedwater or a boiler water sample.  In addition, a finger cot or surgical glove shall be worn for dissolved oxygen testing.

 

3.         Testing, chemical preparation and equipment

 

a.     The testing of feedwater and boiler water samples requires the use of highly concentrated stock chemicals in diluted solutions known as reagents, such as nitric acid, mercuric nitrite, and hardness titrating solution.  Some of the reagents are supplied ready for use and need little or no preparation. For accurate test results, it is necessary that the reagent be prepared strictly according to NSTM 220 V2.

 

b.     Goggles and plastic or rubber gloves shall be worn when pouring stock reagents. Additionally, an apron is worn to prepare dilute caustic soda.

 

K.        Hazardous Material

 

1.         The testing of feedwater and boiler water samples results in the collection of hazardous material.  These chemicals must be collected and disposed of properly.

 

a.     Mercuric Nitrite and Silica One Regent shall be disposed of by turning into     PWC.

 

b.     Hydrazine:  is a known carcinogen and all personnel involved in its handling must be aware of the proper procedures, including the emergency spill clean up procedures.  The use of an enclosed transfer system ensures that personnel receive zero exposure to hydrazine solution or vapors. 

 

(1)   There are two types of stock hydrazine spills, flushable (a spill that can be flushed directly to the bilge or overboard)  and non-flushable. The flushable spill requires the following:  tape off area, place ventilation on high, and flush to bilge. Personnel must remain clear of the bilges until all of the hydrazine is removed.  Non-flushable spill requires taping off the area, spreading absorbent, placing absorbent into plastic bags and then into a drum and turning it over to PWC. The safety gear required for stock hydrazine spills are goggles, gloves, boots, coveralls and an apron.

 

(2)      There are also two types of leaks.  Leakage of stock hydrazine solution (prior to dilution) and leakage of treatment solution (after the  stock hydrazine is diluted with feedwater).  Leakage of stock hydrazine requires the following: place ventilation on high, place bottle in piercing apparatus, and drain the tank to the bilge.  Remain clear of bilges until hydrazine is removed and bilges are thoroughly flushed. Leakage of treatment solution requires the following: tape off area, secure leak, drain tank to bilge, fill tank with condensate, fix leak, hydro system to 90 psi to ensure system integrity. The safety gear for both types of leak requires goggles, gloves, boots and an apron.

L.         Inspections

 

1.         SGPI

 

a.     Boiler inspection done every 18 months (± 6 months)

 

b.     Boiler Overhaul Related Inspections

 

2.         Ship's Force

 

a.     Fireside

 

(1)   Engineer Officer's inspection conducted every 1800-2000 steaming hours

 

b.     Watersides

 

(1)   Boiler watersides shall be water-jet cleaned within 500 steaming hours prior to or after initiation of chelant treatment. The first waterside inspection following initiation of the chelant treatment is required within 2,000 steaming hours of the last inspection.

 

(2)   Following the initial inspection, watersides shall be inspected as part of the 18 month inspection unless one of the following conditions occurs:

 

(a)      Steaming without continuous treatment due to treatment system malfunction for more than 168 steaming hours (continuous), requires that the boiler watersides be inspected during the next upkeep or repair period.

 

(b)      Steaming with moderate-long term contamination requires that the boiler watersides be inspected.

 

(c)      Steaming with boiler water conditions that meet the criteria for significant damage, requires that the boiler watersides be inspected during the next upkeep or repair period. If conductivity exceeds 8,000 mmho/cm, then waterside inspection shall be conducted prior to further operations.

 

(d)      If conductivity exceeds 2,000 mmho/cm, then superheater steam sides shall be flushed and inspected prior to further operations.

 

M.        Off Ship Reports

 

1.         BIRMIS

 

a.     TYCOM Boiler Inspectors report on condition of the boiler inspected.

 

2.         Messages to TYCOM and info ISIC, NAVSEA and NAVSURFWARCEN

 

a.     Continuous Treatment System will be OOC for more than 168 steaming hours.

 

b.     Hideout is suspected.

 

c.     Significant damage.

 

d.     Boiler steamed for more than 8 hours under a condition of serious contamination.

 

e.         Any time the Commanding Officer does not reduce the steaming rate under conditions of serious contamination after one treatment action fails to correct boiler water parameters to moderate contamination or within limits.

 

f.           Deviations from mandatory requirements of NSTM 220.

 

g.         Defective chemical standards.

 

3.         Correspondence to NAVSURFWARCEN and copy to TYCOM, ISIC and NAVSEA

 

        a.     Theoretical conductivity above 30% and source of unusual contamination cannot be determined.