ASSIGNMENT SHEET
BOILER HYDROS
Assignment Sheet Number 62B-233
INTRODUCTION
Hydrostatic
boiler testing is the same for all naval propulsion boilers. Each hydrostatic test serves a definite
purpose to ensure the boiler is safe to operate. Testing must be accomplished everytime the pressure vessel has
been opened for any reason.
LESSON
TOPIC LEARNING OBJECTIVES
Terminal
Objective:
8.0 DESCRIBE
the principles, construction, function, components, control and monitoring
systems, and operation of a conventional steam propulsion plant and associated
auxiliary support systems. (JTI:A)
Enabling
Objectives:
8.178 DESCRIBE
and explain the purpose, preparation and requirements for boiler hydrostatic
testing.
8.179 DESCRIBE
and explain the requirements for the boiler hydrostatic pump, set up and hoses.
8.180 DESCRIBE and explain the requirements for
blank flanges.
8.181 UNASSIGNED; reserved for future use.
8.182 UNASSIGNED; reserved for future use.
8.183 UNASSIGNED; reserved for future use.
STUDY
ASSIGNMENT
1. Read Information Sheet 62B-233.
2.
Outline Information Sheet 62B-233 using the enabling objectives for
lesson 62B-233 as a guide.
3. Answer study questions.and scenarios.
STUDY
QUESTIONS
1. What is the purpose of any boiler hydrostatic
test?
2. What are the requirements for the
hydrostatic test pump?
3. State the order in which multiple
boiler hydrostatic tests should be applied.
STUDY
SCERINOS
While
standing EDO inport cold iron you are informed that the engineers will be doing
a 135% hydrostatic test on 1A boiler.
1. What
work would have been done in order for the engineers to do a 135% hydrostatic
test?
INFORMATION SHEET
BOILER HYDROS
Information Sheet Number 62B-233
INTRODUCTION
Hydrostatic
boiler testing is the same for all naval propulsion boilers. Each hydrostatic test serves a definite
purpose; to ensure the boiler is safe to operate. Testing must be accomplished everytime the pressure vessel has
been opened for any reason.
REFERENCES
(a)
Boilers NSTM Chapter 221
(b)
Boilerwater/Feedwater Chemistry
NSTM Chapter 220 V2
(c)
Repair and Overhaul Main Propulsion Boilers S-9221-C1-GTP-010
INFORMATION
A.
Purpose
1.
The object of boiler hydrostatic tests is to
demonstrate either tightness or strength of the boiler and its parts. The tests apply to, and include, the entire
boiler pressure vessel. This includes
the first or most proximate valve on each connecting line to the boiler. This valve may be any one of the
following: safety valve, bottom blow
valve, surface blow valve, main steam stop, auxiliary steam stop, superheater
protection steam inlet and outlet valve, chemical feed valve, vent valve,
direct and remote water gauge cut out valves, pressure and temperature gauge
connections, drain or feed valves.
Piping on opposite sides of these valves is discussed in Piping Systems
NSTM Chapter 505.
2.
Hydrostatic test pressures for a particular
boiler can be determined by reference to the design and operating data listed
in reference (c). Each boiler
hydrostatic test pressure has a definite purpose. Testing too often or at pressures higher than required to prove
the test objective increases the risk of damage to the boiler and injury to
personnel
B.
Desuperheater
1.
Prior to conducting boiler hydrostatic testing,
the desuperheater shall be hydrostatically tested to 150 psig or the maximum
operating differential pressure for the assembly, whichever is higher. This test is for tightness at the joint or
tube seats when the assembly is installed in the boiler. If repairs were conducted on the assembly it
shall be tested to 150 percent of the desuperheater design pressure or 350 psig
if data is unavailable. This is to
verify tightness of the repairs. This
test is usually conducted with the unit removed from the boiler.
C.
Preparation
1.
To prepare a boiler for hydrostatic test, flush
it out with feedwater or potable water using a hose at a pressure of
approximately 50 psig. Flush the steam
and water drums, the gage glass through drum penetrations, and all tubes and
headers to remove all loose deposits.
2.
A careful examination of the boiler shall be
made to ensure no tools are left in the boiler.
3.
Ensure that all gasket, handhole, and manhole
surfaces are clean and remake all joints.
4.
Blank or gag all safety valves when the boiler
is subjected to hydrostatic test pressures above operating pressure. To minimize bent valve stems, it is
recommended that the valves be blanked off rather than gagged for hydrostatic
tests above 100 percent operating pressure.
Blanking is required for 150 percent of design tests.
5.
Before applying a hydrostatic test, close all
connections on the boiler except the air vent, direct reading water gauge, test
pressure gauge, and valves in the line through which pressure is to be
applied. When applying a 150 percent
hydrostatic test, the direct reading water gauge connections shall be shut.
6.
The safety valves and boiler blow valves shall
be removed and blanked. All blank
flanges used to blank off any opening in the boiler, including temporarily cut
large tubes or piping, must be in accordance with NAVSEA drawings.
7.
Feedwater used for hydrostatic testing should be
between 20°C and 50°C (70°F and 120°F).
The danger in using hot feedwater for hydrostatic tests is that water
spraying from leaks can flash into steam and injure personnel. Warm the feedwater in the deaerating feed
tank (DFT) with steam or use an independent mixing tank to heat the water
before filling the boiler.
D.
When using deaerated feed water for hydrostatic
testing, omit the addition of sodium nitrite to avoid excess concentration of
this chemical in the boiler. Also omit
the addition of sodium nitrite if the hydrostatic test is to be applied within
36 hours of securing from ethylene-diamine-tetraacetate (EDTA) cleaning or the test
is to be applied during sodium nitrite wet layup. The boiler shall be
completely filled with heated water and entirely free of air before pressure is
applied. Air is removed by keeping vent
valves open on the steam drum until a steady stream of water flows from
them. The boiler metal temperature
should not fall below 70°F during the hydrostatic test. Hydrostatic tests performed by depot level
activities shall be conducted using feed quality water. Hydrostatic tests performed by ship's force
should be conducted using feedwater treated or untreated with sodium nitrite
that meets the requirements of NSTM chapter 220 V2. However, if sufficient feedwater is not available, ship's force
may use fresh water.
E.
Applying pressure
1.
The test pressure shall be applied by a special
high pressure, low capacity hand operated, or pneumatic‑operated
hydrostatic pump. The main feed pump
should not be used for hydrostatic testing except in emergencies when an
operable test pump is not available. If
the main feed pump is used it shall be limited to the 100 percent maximum
steady state operating pressure test.
2.
The test pressure should be increased slowly to
prevent over pressurization. The test
pressure should be maintained at least 15 minutes before conducting the
inspection of pressure parts. Pressure
should be increased slowly and applied carefully to avoid exceeding the test
pressure. A boiler shall not be tested
to a higher pressure than required by the test objective. The pressure to be applied shall not exceed
1‑1/2 times the boiler design pressure under any circumstances.
3.
An operator shall be stationed at the test pump
regulating valve and pressure gauge during the entire test to monitor and
regulate hydrostatic test pressure to prevent over pressurization. A drain should be used to regulate the
boiler pressure by bleeding excess supply to the bilge. The test pressure should be maintained at
least 15 minutes before beginning the inspection of the boiler to minimize
personnel exposure to boiler component failure or sudden leakage. The test should last just long enough to
accomplish the inspection.
4.
If the boiler is to be tested at pressures
higher than the 100 percent maximum steady state operating pressure, the
highest pressure shall be applied first and then the next test pressure applied
in descending order. The last test
shall be a tightness test at 100 percent maximum steady state operating
pressure. Inspection of all boiler
joints and fittings shall be conducted during this tightness test. Following a 135 percent hydrostatic test,
replace individual gaskets that leak however, it is recommended to replace all
boiler gaskets. Upon completion of a
150 percent hydrostatic test, all boiler handhole and manhole gaskets shall be
replaced. The gaskets have to be
replaced because the high pressures have over compressed the gaskets and this
contributes to failure during operation.
F.
Safety Precautions
1.
Ensure that there is no leakage past the main or
auxiliary steam stop valves.
2.
Compression of trapped air within the boiler
during hydrostatic test pressure buildup can lead to an extremely dangerous
situation and may prevent achieving the required pressure. Compression of trapped air could result in
extensive damage and possible personnel injury in the event of a pressure part
failure.
3.
During the hydrostatic test of the boiler, the
desuperheater shall be filled with water and pressurized along with the boiler
to prevent exceeding the design pressure of the assembly. This requires that the desuperheater inlet
valve be open during the test.
4.
While under 150 percent hydrostatic test
pressure, the boiler should be subjected to an external visual examination to
detect structural defects such as gross leakage, bulges, or distortions or
cracks in welds, nozzle connections, and renewed or repaired pressure
parts. Sufficient casing panels shall
be removed to permit the visual examination.
Inspection of all boiler joints and fittings shall not be conducted
during this test. Upon completion of
the 150 percent hydrostatic test, a close visual examination of the boiler from
the outside and inside shall be made of welds, nozzles, connections, and
reworked or repaired pressure parts. Do not enter the boiler when under
pressure for 150% hydrostatic test.
G.
Hydrostatic test acceptance criteria is as
follows:
1.
Newly installed rolled tubes are required to be
dry.
2.
Old tube joints (that is, other than newly
installed) need only satisfy the 100 percent hydrostatic test for leakage. Dampness (that is, a slight ring around a
rolled tube joint) with no weep, spray or trickle is not considered to be a
leaking joint.
3.
If pressure loss is high and only slight leakage
exists through the tube joints and gaskets, the loss is due to leaky valve(s)
or fitting(s) and these should be overhauled as necessary.
4.
Continued gasket leakage can cause damage to the
seating surfaces, making follow‑on repairs more expensive. The leakage criteria for boiler handholes
and manholes at the 100 percent maximum steady state operating hydrostatic test
pressure are as follows:
a)
For operating ships, the leakage rate is
preferably zero, but shall not exceed three to five drops per minute.
b)
For ships in an availability that includes a
boiler overhaul, the leakage rate for repaired or resurfaced handhole and
manhole seats shall be zero (bone dry).
H.
Economizer
1.
The economizer is usually tested along with the
boiler unless the test is for specific repairs on the economizer. Some repairs require the economizer to be
tested at 150% of design pressure. If
testing the economizer at 150 percent of design pressure is to be conducted,
the economizer shall be isolated to prevent application of an unnecessary
pressure on the boiler.
2.
The hydrostatic test pump and fittings shall
comply with minimum requirements as follows:
3.
All hoses and fittings shall meet either
military specifications or the Society of Automotive Engineers (SAE)
specification if purchased from an outside vendor.
4.
A minimum of one method of manual over pressure
protection shall be provided for every hydrostatic test and at least one means
of backup over pressure protection is required (manual or by relief
valve). Boiler maintenance manuals
specify that a safety relief valve should be installed downstream of the
shutoff valve.
5.
All flexible hoses should be identified and
labeled according to Piping Systems NSTM chapter 505, and tagged with a warning
sign stating "for use with hydrostatic test pump only".
6.
The hydrostatic test pump and related
accessories should be covered and stored in a cool dry area.