INFORMATION
SHEET
TURBINE/GEAR
MAINTENANCE
Information
Sheet Number 62S-103
INTRODUCTION
The Main Engine and Reduction Gears
are two of the most simply designed pieces of equipment in the propulsion
plant. Although their design is simple,
they are two of the most important pieces of equipment on board a ship. Without the main engine and the reduction
gears a ship is unable to get underway or maneuver. The maintenance and thorough monitoring of these components are
paramount to safe and prolonged operation.
There is nothing that can be done to an operating engine and reduction
gear while operating other than to maintain the lube oil's cleanliness and to
monitor and record the various readings taken.
These readings are the key indicators used to determine what maintenance
is required and needed.
1.
Information in this student guide complements MRCs, information in NSTMs
and manufacturer's technical publications.
2.
Where PMS coverage applies, preventive maintenance will be accomplished
in accordance with MRCs. The MRC
supersedes all other procedures. It
should be noted that PMS is the minimum required, the Engineer Officer can
always demand more, but PMS is very detailed and precise throughout the fleet
on main engine maintenance.
3.
NSTMs, manufacturer's equipment manuals, ship's information books,
blueprints, and applicable documents (TYCOM maintenance manuals/instructions,
etc.) will provide detailed procedures for maintenance, inspections and tests.
4.
These publications also provide information for the evaluation of tests
and inspection not covered by MRC's.
REFERENCES
(a) Reduction
Gears Technical Manual NAVSEA 0951-LP-022-6010
(b) Propulsion
Turbines NSTM Chapter 231
(c) Propulsion
Reduction Gears, Couplings, and Associated Components NSTM Chapter 9420
INFORMATION
A.PURPOSE OF MAIN ENGINE/REDUCTION GEAR
MAINTENANCE. The maximum operational
reliability and efficiency of an engineering plant requires a planned program
of inspections, not only to discover parts that may fail at a critical time,
but to eliminate underlying conditions such as misalignment, corrosion, erosion
and improper fabrication.
1.
RESPONSIBILITY OF THE ENGINEER
OFFICER
a.
The Engineer Officer's knowledge and supervision directly affects this
program of inspections and maintenance.
He/she must insure that the proper techniques were used and that the
data derived from the inspections are properly interpreted.
b.
Engineering maintenance is the coordination of many parts; technical
knowledge, i.e. corporate knowledge and technical skills of personnel, (PMS)
and of course publications and references.
c.
Engineering planned preventive maintenance has been formalized but it
must be understood that this program is only the minimum requirement.
d.
An Engineer Officer should have an in-depth understanding of the PMS
requirements and insure supplemental maintenance is accomplished to insure
equipment reliability and safe operation.
e.
Training should also be considered as part of a proper engineering
maintenance program. The training
should not only include proper maintenance procedures but also information that
will insure that the equipment is operated under the proper procedures and
parameters.
2.
TURBINE MAINTENANCE
a.
NSTM Chapter 231 Propulsion Turbines is the "bible" for all
maintenance actions, inspection procedures and casualty control procedures for
main turbines. Taken from the NSTM is a
table showing turbine maintenance items and the purpose for each. Periodic tests and inspections have been
developed that will insure the items listed are covered (see Figure 1).
MAINTENANCE ITEMS AND PURPOSE TABLE
|
ITEM |
PURPOSE |
|
Verification of radial and axial
position of the rotor by appropriate clearance methods |
Avoid internal rubs that can make
equipment inoperable |
|
A clean lube oil system and the proper
lubricant quality and quantity |
Avoid wiping of bearings, scoring of
journals and thrust collar and chemical attack on those and other critical
surfaces |
|
Freedom of turbine controls |
Avoid slow action or hag up of
throttles |
|
Check condition of oil deflectors and
waste oil drains |
Avoid ingress of oil into steam system |
|
Check condition of water drains |
Avoid ingress of water into lubricating
systems, blade erosion and water slugging |
|
Check cleanliness of machinery
internals |
Avoid ingress of foreign material
through access openings or through connected piping, which restricts internal
damage (mechanical or chemical) |
|
Check condition of shaft and gland
packing |
Avoid blowing steam into engineroom or
pulling air into turbine or condenser |
Figure
1
PERIODIC
TESTS AND INSPECTIONS
|
TESTS/INSPECTIONS |
FREQUENCY |
|
Operate LO purifier while underway |
Daily |
|
Operate and lubricate all valve operate
linkages |
Monthly (if secured) |
|
Take micrometer readings on the journal
bearings of the main propulsion turbines |
Quarterly |
|
Lift sentinel and relief valves by hand |
Quarterly (some platforms are
semi-annual) |
|
measure main turbine thrust clearance |
Annually |
|
Inspect interior of turbine casing |
Regular overhaul or if damage is
suspected |
|
Clean, inspect, interior of turbine
casing |
Regular overhaul cycle |
|
Inspect main propulsion bearing
journals and oil deflectors measure clearances |
Annually and regular overhaul |
|
Inspect shaft packing and journal for
condition, check clearances |
Regular overhaul cycle |
|
Foundation bolt tightness |
Regular overhaul |
|
Drain and refill operating control gear
boxes |
Annually and regular overhaul |
|
Remove and clean main steam strainer |
Regular overhaul |
|
Measure nozzle clearance |
Regular overhaul |
|
Test high and low pressure turbine
sentinel valves |
Annually or regular overhaul |
Figure
2
a.
The next table (see Figure 2) lists periodic tests and inspections for a
turbine. This is a sampling of items
and all of these items are covered under the PMS system.
b. Propulsion
Turbines are basically designed machines.
The dynamic loading and transient conditions applied to main turbines
make the inspections and maintenance vital to safe and prolonged operation. The main engine is always in operation while
underway, unless a casualty occurs. The
only time preventive maintenance can be completed is inport, with the engine
secured. Through proper scheduling, a
majority of the required maintenance can be accomplished at the same time. This should give the Engineer Officer and
MPA a "warm fuzzy", as they will be aware of the exact status of the
main engines, including all of the measurements and clearances. This information can be vital to the
Engineer Officer if a casualty occurs.
c.
The Engineer Officer will find very few actions that ship's force can do
to a main turbine. The review of
operating logs and the maintenance of clean lube oil are the best things for
the turbine. The actual inspection of
the turbine internals and casing is performed by the Engineer Officer using the
MRC. Prior to the inspection, the
Engineer Officer needs to review the MRC and NSTM 231. These documents aid the Engineer Officer in
the inspection and assists in the recording of the material history by using
standardized terms.
d.
During the inspection, the Engineer Officer is only able to see about
10-25% of the HP turbine internals and 40-60% of the LP turbine internals (see
Figure 3 as a guide). Access ports
allow viewing of the 1st stage area, the exhaust end of the HP and a view of the
balance weights. The access ports at
the steam inlet or first stage are very small and provide a limited amount of
area to be seen. This is due to the
casing halves being together and the turbine internals obstructing some of the
view. A borescope can be useful in this
area, if one is available. The access
ports on the LP turbine are considerably larger and provide a more extensive
look inside. The major areas that can
be observed are the astern elements, the exhaust of the LP and astern elements
and the diaphragms and supports.
TURBINE
INSPECTION GUIDE
|
TURBINE
PART |
LOOK FOR THE FOLLOWING |
|
Interior
surface of casing |
Corrosion,
erosion, condition of casing steam seal surfaces |
|
Nozzle
diaphragms |
Erosion/corrosion
of horizontal parting and vertical steam seal surfaces, condition of
radial/axial crush pins.
Erosion/corrosion pitting and cracking of vanes |
|
Diaphragm
and gland packing rings (carbon and labyrinths) |
Wear,
freedom of movement, condition of springs, position relative to the rotor |
|
Rotor
blading and shrouding |
Cracks,
dents, tears, erosion, corrosion, lifting of the shroud, integrity of
stellite shields, axial and radial rubs |
|
Rotor |
Surface
cracks of chromed or spray metalled areas.
Balance weights intact and firmly anchored. Erosion/corrosion of packing areas and integrity of end plugs
on hollow rotors. Journal
condition (scoring, wear, pitting) Thrust collar (scoring, wear, pitting, tightness) |
|
Journal
Bearing |
Wear,
loose babbitt, contact pattern, scoring, tin oxide, RTE intact |
|
Thrust
Bearing |
Shoe
wear, loose babbitt, contact pattern, scoring, wear of leveling plate
supports, RTE intact |
|
Blading
radial seals |
Wear,
pieces broken out, firmly seated |
|
Horizontal
joint (main and nozzle chest) |
Steam
cutting, evidence of leaks |
|
Casing
structure |
Cracks
in casing, particularly in the HP first stage shell area and floor of main
steam chest. Cracks in casing support
plates, welds, flex, plates. Proper
clearance for and freedom of keys and sliding feet. Distortion of gland housing. |
|
Valves
(nozzle, bypass transfer, extraction and drain) |
Scoring
of lift rods in way of bushings.
Condition of stems that may indicate leakage or hang up. Wear of linkages, bearings and cams |
|
Rotor
position differential expansion indicators |
Wear,
adjustment, calibration |
|
Nozzle
blocks |
Cracks
in ligaments between reamed nozzles.
Both retainer plates out of position.
Loose or broken bolts |
Figure
3
a.
Three things can be useful to the Engineer Officer during a turbine
inspection: the use of Morpholine or a
corrosion inhibitor when operating; reviewing of the operating logs and
knowledge of where damage is most probable.
Morpholine or some corrosion inhibitor is carried over in the steam
supplied by the boiler. This
"coats" the piping and equipment internals. These components become either a light gray or brownish in
appearance. The Engineer Officer should
be looking for a difference in color.
Cracking, erosion or corrosion affect this protective layer and the
color will appear different. The
Engineer Officer should be keying in on this, as it is hard enough to see the
turbine internals. He or she should be
aware of this fact and how it will help them.
Also, the use of corrosion inhibitors has greatly reduced the problems
encountered by corroding materials and this problem is almost non-existent now.
b.
The review of operating logs against design limits provided in the main
engine technical manuals can help identify possible steam flow problems. Abnormal pressures and temperatures can be
used to highlight suspected problem areas.
If journal bearing clearances are satisfactory, there should be no
problems in the turbine's steam flow.
The flow design of the turbine is dependent on the alignment provided by
the bearings.
c.
The probability of damage or wear is greatest where the highest
pressures and temperatures occur. This
area is easy to find; the HP first stage and nozzle block (the small access
ports allow viewing this area) and the astern elements of the LP turbine (large
access ports show this). If there is no
damage in these areas, it is a safe bet that the rest of the turbine is okay
(as each stage of the turbine there is a pressure drop and temperature is
decreased). This area should be of
primary interest to the inspector.
d.
Important considerations behind the requirements for turbine PMS are
maintaining the design steam path clearances and insuring proper axial and
radial clearances. As stated earlier,
operating logs can be very useful at this point. The two components used to maintain alignment are thrust bearings
and journal bearings.
e.
Axial clearances are designed to allow for turbine rotor/casing
expansion, contraction, and movement.
This movement is limited by use of a Kingsbury type thrust bearing on most
platforms. Axial clearances can be
checked both during operation and when the turbine is idle by using the rotor
position indicator. This reading
provides a "quick look" or reference of axial alignment.
f.
Radial position and alignment of a turbine is maintained by the use of
journal bearings. Excessive wear or
damage to journal bearings can cause extensive problems inside a turbine, much
more than average problems experienced by a damaged thrust bearing. The thrust bearing's maximum clearance is
only half the distance between the casing and blading, this allows some safety
margin. Once the journal bearing is
damaged, the shaft "drops" and rests on the internal components
(gland seal and diaphragm labyrinths).
This damage affects the seals and steam flow through the turbine. Watchstanders might find this by their
hourly readings. If you notice an
increase in gland seal steam, blow by of steam from the glands or slightly
abnormal bearing temperatures, you should investigate. It is important to realize, that once the
internal labyrinths are damaged there is generally little you can do. The ship's force, on most platforms can only
change out or repair the outer set of labyrinths, because the turbine casing
allows no access to the others.
Maintaining the radial position of the turbine and reduction gear
components within design limits prevents damage to:
(1)
Turbine casing
(2)
Turbine blading and shrouding
(3)
Turbine diaphragm and packing rings
(4)
Turbine oil deflector rings
(5)
Reduction gears due to mis-alignment
g..
Propulsion turbines are balanced to a "T" prior to assembly in
a ship. As long as all operating
parameters are within specifications, the turbine will last for a long
time. If something goes wrong with a
turbine, sight and hearing will probably be the first indication of something
wrong. Your watchstander is the first
line of defense. Does he or she know
this?
h.
The way a turbine is operated can affect the maintenance and reliability
of the turbine. A rotor should never
sit still for more than 5 minutes after steam has been admitted. If a turbine in operation should suddenly
vibrate, the problem could be any one of the following:
(1)
Water in the turbine
(2)
Bearing failure
(3)
Bent or broken propeller blades
(4)
Unbalance due to broken or missing rotor blades
(5)
Rubbing of blading labyrinth packing or seal rings
(6)
Bowed rotor
i.
If you hear a rumbling sound and the turbine begins to vibrate, it is
probably water or foreign material. But
it is important to know that vibrations or noises from either the turbine or
shaft can travel to the reduction gears.
This greatly affects the watchstanders in their troubleshooting.
j.
Sometimes the Engineer Officer might feel an internal inspection is
needed if the noises or vibrations were excessive (prolonged operation while
bowed or with an excessive vibration can be a contributing factor). A sure sign of something rubbing on the
rotor will be a shiny spot on the rotor (that difference in color again). If this is noted during an inspection,
immediately investigate the cause and correct it.
k.
When rubbing of a turbine blade or labyrinth occurs, the cause will
probably be a bowed rotor. Other causes
could be:
(1)
A defective thrust bearing (usually noticed in an RPI reading)
(2)
A wiped journal bearing (possible problems with gland seal steam)
(3)
Foreign material inside the casing (Equipment close-out sat?)
(4)
Differential in the amount of expansion between the casing and the rotor (proper warm up of the
turbines can prevent this)
l.
A lot of these problems are preventable by operating safely in
accordance with EOSS. The satisfactory
operation of a turbine depends largely upon the axial and radial alignment of
the rotor in the casing. During normal
operations, the temperature of the oil leaving the bearing is the sole
criterion available to the operator for judging the conditions of the various
bearings. Oil temperature leaving a
bearing will vary depending on the changes in speed, especially since all
turbine and reduction gears are sliding surface contact bearings. These bearings develop a lot of heat due to
friction and are dependent upon proper quantity and quality of the
lubricant. Thus, keeping the lube oil
quality at it's best is vital to prolonged operation. Over a period of time you should be able to chart the changes and
detect any bearing that may be out of specifications (reviewing of operational
logs again).
m.
If it is suspected that one of the bearings is out of specifications,
when the turbine is secured you can take a "quick look" at the
bearings. A depth gage is the quickest
and easiest means to determine the amount of wear on a journal bearing. When a bearing is first installed, make a
measurement on the bearing to act as a base point. Log this reading. This is
your reference point. Never make
repairs to a bearing solely upon the outcome of a depth gage reading. If a depth gage reading shows up bad, then
make other measurements to the bearing before trying to make repairs.
n.
If other measurements are required besides a depth gage, then the
bearing will need disassembly and inspection.
Some journal to bearing rubbing contact is made on each start. A good bearing will show a polished area
centered in the lower half of the bearing.
Discoloration of bearing surfaces almost always indicate a lubrication
problem. Moisture in the oil and
operation under high temperatures can produce a tin oxide coating on the
bearing. This coating is very hard and
builds up to reduce bearing clearance.
o.
If a bearing is to be replaced, ensure the spare meets all the design
specifications prior to reassembly.
When removing an old bearing, do not lift the rotor more than .005 inch. Lifting the rotor too much will damage the
shaft packing. The new bearing must be
reassembled properly. You can put a
bearing in backwards. This could lead
to another casualty due to lack of lubrication.
p.
The easiest way to measure the axial clearance is by the installed Rotor
Position Indicator. Another means would
be to position a dial indicator against the rotor and jack the rotor fore and
aft three times, using the average of the three. If there is an indication of a worn thrust bearing, then remove
the cover to the bearing and make a feeler gage measurement of the bearing. If a bearing needs to be repaired, then
repair all surfaces, make new measurements and shim the bearing to ensure it
meets all specifications on oil clearances.
q.
Most inspections of the turbine internals will be done through access
covers. there are two times when you
would remove the turbine casing. The
first is when there is knowledge or suspicion of internal damage. In this case you should get technical
determination of the necessity to disassemble from NAVSEA. NAVSEA will review your operating logs, take
their own readings to discover what is going on with the turbine and its'
internals. The second time would be
three months prior to overhaul and then NAVSEA will again repeat the process to
see if lifting the casing is absolutely necessary. Submit a report to the type commander about the condition of the
turbine. In both situations the type
commander should be aware of the condition of the turbine and will make the
final authorization, after he has all the information, to lift the
casings. If it is not absolutely
necessary, an alternate maintenance action will take place due to the cost of
lifting the turbine casing.
r.
Whenever there has been a main propulsion turbine opened for repair or
inspections, the work is not complete until a dock trial and post repair trial
has been satisfactorily completed. The
Engineer Officer of each ship will issue instructions for operating the plant
during a dock or post repair trial.
s.
The trial will go something like this.
Install muslin bags in the lube oil strainers and determine the
frequency to which these are to be changed.
Once the muslin bags are found to be clean, then engage the jacking
gear. Station personnel around the
turbine to detect any unusual conditions or noises. If none exist, then consider the turbine ready to do a dock
trial.
t.
For the dock trial the Commanding Officer will determine the maximum
number of RPM's he/she wants the shaft to go.
The Engineer Officer determines the amount of time needed to warm up the
main engines and when ready, notifies the OOD.
The bridge determines the number of RPM's and slowly increases to the
maximum RPM allowed. If there are no
difficulties, then the turbine would be ready for a post repair trial.
B.MEASUREMENT METHODS FOR TURBINE/GEAR
BEARINGS
a.
Journal bearings can be measured in a few ways. these are the ways available to determine
bearing clearances:
(1)
The Depth Micrometer Method.
This is the quickest method to get an indication of ring wear. These is no disassembly of the bearing. The turbine must be isolated and secured
from rotating and the lube oil system must be secured for at least 24 hours
prior to taking the measurement.
NOTE: This method is only a
quick check and should not be used as a final method of determining bearing clearances.
(2)
The Bridge Gage Method. This
method requires the component to be placed out of commission and
disassembled. It is used when there is no
access for a micrometer in the bearing.
This requires two personnel to perform and is not as accurate. Only a few ships use as the method for
taking measurements.
(3)
The Crown Thickness Method. This
method requires disassembly of the journal bearing. The bearing is rolled out of the component and a micrometer is
used to take readings of the bearing thickness at scribed lines on the side of
the bearing shell. A drill bit or round
object is needed also. The micrometer
has a square face and the bearing shell has a rounded shape, the drill bit
allows the measurement to take place.
(4)
The Leadwire/Plasti-gage Method.
This method requires the component to be placed out of commission and disassembled. Leadwire/Plasti-gage method is used
primarily on spring bearings which do not have a bridge gage assembly or access
hole for a depth micrometer and because of the size and location of the spring
bearings.
(5)
The OD and ID Method. The
bearing is disassembled and the inside of the bearing is measured. The outside of the shaft is measured. The clearance is the difference between the
two. This method is very accurate,
allowing the bearings wear pattern to be checked. It is recommended to go from a depth micrometer reading to this
method as final verification of readings.
b.
Thrust Bearings can be measured in few ways. The following methods are available:
(1)
Rotor Position Indicator. A
"Quick" method for checking rotor position without disassembly. This reading can be taken while the rotor is
rotating or idle. The reading gives the
relative position of the rotor and is not intended for PMS purposes. Readings are recorded hourly by
watchstanders on the main turbines and cold/hot readings of the rotors are
recorded during plant start-up.
(2)
Thrust Bearing Oil Clearance Method.
In this method the turbine must be secured and at ambient
temperature. The lube oil system must have
been secured for 24 hours, and the thrust bearing has to be intact. The rotor is jacked forward and aft and dial
indicator readings are taken. The
clearance is the total travel of the rotor.
(3)
Taper Gage Method. The turbine
must be secured and access to the turbine blading opened. This method is considered accurate but not
as good as the oil clearance method due to the experience of the mechanic. The tape gage is inserted between the first
stage nozzle and the moving blade. The
gage, having been coated with prussian blue, is then taken out and the area
with no blueing is read. This is known
as the nozzle blade clearance.
(4)
Thrust Bearing Inspection. A
lengthy method where the thrust bearing is disassembled and visually inspected
for wear. This inspection should only
be used when one or more of the previously discussed methods indicate excessive
thrust clearances.
C.SPECIAL TOOLS FOR INSPECTION AND
CLEARANCE MEASUREMENT
a.
Outside Micrometer. It is a
precision instrument calibrated in .001 inch increments. The outside micrometer is used to measure
outside diameters of rod shaped materials or the thickness of flat materials.
b.
Depth Micrometer. A precision
instrument calibrated in .001 inch increments and is used to measure depth of
distance from a pre-described step.
This reading usually requires verification from another method.
c.
Reading of the Micrometer. The
sleeve is marked off in .025 inch increments from 0 to 1 inch. Each numbered mark indicated is .100 inch. The thimble is divided into 25 equal
units. One revolution moves the spindle
a total of .025 inch.
(1)
Steps in reading the micrometer:
(a)
Count the "numbered lines showing on the sleeve, and multiply the
total by .100 inch.
(b)
Count the lines showing between the last "numbered" line and
the thimble. Multiply the number of
marks by .025 inch and add it to the value obtained in the first step.
(c)
On the thimble, locate the line nearest to the horizontal line of the
sleeve. Multiply this value by .001
inch and add it to the value obtained in the first two steps.
EXAMPLE
a) 3 x .100 in. = .300 in.
b) 2 x .025 in. = .050 in.
c) 6 x .001 in. = .006 in.
.356 in.
d.
Bridge Gage. A precision
instrument machined for bearing wear measurement. It is used in conjunction with an inside micrometer, reading a
distance form designated landing to journal.
Wear of the bearing is the difference between the reading obtained and
constant stamped on the bridge.
e.
Leads/Plasti-gage. Leads are
wire made up of soft un-alloyed lead.
It comes in various thicknesses and usually on a roll. This material is being phased out, being
replaced by a plastic gage serving the same purpose and easier to interpret
when taking measurements.
f.
Taper Gage. A taper gage tool is
a wedge shaped tool calibrated in .010 inch increments. It is used to measure clearance between
blading and casing of turbine.
g.
Dial Indicator. This instrument
is made up of a calibrated dial (increments of .001) and several components
that allow a wide variation in the attachment.
This is used to check rotational, vertical and horizontal alignment.
2.
BEARING TERMINOLOGY. These terms should be used when recording
material history. These are the
standardized terms found in the NSTM, use of these makes it easy for future personnel
to understand your intent.
a.
CONSTANT: A reference, or
baseline depth micrometer measurement.
A constant is established only upon reassembly after bearing replacement/renewal
or disassembly for inspection during which the clearance has been verified to
be within design specifications. The
constant does not change until the bearing is again disassembled and a new
constant is established.
b.
CLEARANCE: The difference
between the inside diameter of a bearing and the outside diameter of its
associated journal. These diameters are
initially determined by calculating the averages of four measurements taken on
each piece.
(1)
Subsequent depth micrometer measurements taken on an in-service bearing
will reveal the gradual increase in clearance which occurs as the bearing
wears.
(2)
Proper clearance is critical to proper lubrication of a bearing.
c.
WEAR: The increase in clearance
which occurs during the service life of a bearing.
d.
SUMMARY: The bearing constant is
the reference depth micrometer measurement from the machined boss surface to
the top of the journal when the clearance is known to be within design
specifications. The constant and the
associated clearance must be recorded.
(1)
A subsequent depth micrometer measurement taken on an in-service bearing
is compared with the constant to determine wear and thus the new
clearance. A depth micrometer measurement
taken on an in-service bearing will normally be larger than the constant. The difference between these two is the
total wear, or increased in clearance, which has occurred since the constant
was established. Original clearance
plus total wear yields the new clearance, which must be checked against the
allowable maximum. Excessive clearance
requires bearing work.
(2)
A decrease in clearance could be an indication of a wiped bearing, and
must be investigated.
3.
SETTING ROTOR POSITION
INDICATORS. A rotor position indicator
(RPI) is used to determine the rotor position in relation to the turbine
casing. RPI's are located at the forward
ends of the HP and LP turbines. When
initial installation of the unit is completed, technical data is supplied which
lists specific clearances at blading, casing and unit axial clearances. These readings are used to reset rotor
position indicators and are crucial if thrust bearing repair or replacement
occur.
a.
PROCEDURE FOR SETTING ROTOR POSITION INDICATORS
(1)
PERMISSION. Permission to enter
turbine bearing housings must be obtained form the Engineer Officer. This authority cannot be delegated. This must be granted if accomplishing thrust
bearing clearance PMS or resetting indicators if thrust bearing repair or
replacement is needed.
(2)
SECURITY. Tag out and
de-energize all equipment in accordance with current shipboard
instructions. Inventory all tools and
equipment before performing maintenance.
Thoroughly clean area around bearing housings. Tether and secure all objects, remove all objects from pockets,
and jewelry from person. Do no leave
open gear case unattended, and maintain security watch in immediate
vicinity. A responsible petty officer
E-5 or above is required.
(3)
INITIAL INDICATOR SETTING/INDICATOR REPLACEMENT (NO CHANGE IN AXIAL
POSITION OR THRUST BEARING CLEARANCE).
When at ambient temperature, jack the turbine rotor fore and aft three
times, measure total axial movement using a dial Indicator. Take the average of three readings to
determine rotor thrust, and record.
Jack the turbine rotor forward, and zero the rotor position
indicator. No further adjustments are
needed and the rotor position can be determined directly by pressing the
plunger on the indicator.
(4)
SETTING INDICATOR IN ACCORDANCE WITH THRUST BEARING REPAIR OR
REPLACEMENT. If the thrust bearing
measurement is out of clearance, repair or replace in accordance with MRC or
applicable technical manual. Measure
thrust bearing clearance in accordance with applicable MRC. Remove bearing housing, at ambient
temperature jack turbine rotor fore and aft three times. Measuring axial movement using a dial
indicator. Take the average of three
readings to determine rotor thrust and record.
Jack turbine rotor forward and zero rotor position indicator. Thrust bearing total clearance must be known
and recorded to again reset indicator or the reading will not be accurate. No further adjustments are needed and rotor
position can be determined directly by pressing the plunger on the indicator.
4.
FLEXIBLE COUPLING MAINTENANCE AND
INSPECTION. Flexible couplings are used
to transmit the torque from the propulsion turbines to the reduction gear and
allow for small misalignments between the two.
Flexible couplings are usually of the Dental or Fine tooth type. Lubricating oil is supplied to the teeth
from the adjacent bearing feed line or by separate nozzles.
a.
FLEXIBLE COUPLING INSPECTION.
Two major areas looked at by the Engineer Officer are the distance piece
sliding clearance and the gear teeth backlash.
If either of these are unsatisfactory, the transmission of torque or
prevention of thrust reaching the reduction gears can be affected.
(1)
PERMISSION to enter the reduction gears must be obtained from the
Engineer Officer. This authority cannot
be delegated.
(2)
SECURITY. Tag out and
de-energize all equipment in accordance with current shipboard
instructions. Inventory all tools and
equipment before performing maintenance.
Thoroughly clean area around the coupling cover and reduction
gears. Tether and secure all objects,
remove all objects from pockets, and jewelry from person. Do not leave an open gear case unattended,
and maintain security watch in immediate vicinity. A responsible petty officer E-5 or above is the minimum
requirement.
(3)
REMOVE INTERFERENCE. Remove
piping/interference and oil seal/packing rings. Inspect oil seal/packing rings for cuts and tears. Remove the upper coupling cover and aft
bearing housing upper half. Rig a
lifting strap to support the coupling distance piece.
(4)
TO INSPECT COUPLING TEETH, move the coupling shaft (distance piece)
forward or aft to permit maximum inspection of coupling teeth. Any tooth damage which impairs sliding
requires coupling repair or replacement.
(5)
MEASUREMENTS OF COUPLING FLOAT.
Clean and ensure the distance piece will slide the full length of
travel. Raise the distance piece enough
to remove the weight from the coupling sleeves. Move the distance piece hard aft using a rapid motion (a metallic
ring should be heard when the distance piece bottoms), then move the distance
piece forward. Position the dial
indicator against the after surface forward coupling hub; zero the
indicator. Slide the distance piece to
the extreme aft position, observe and record reading. Repeat the sliding and measurement steps three times and record
the average reading. Remove indicator
and lower distance piece.
(6)
BACKLASH MEASUREMENTS. Install a
strap wrench, take up backlash between coupling teeth. Insert thickness gage on opposite side of
tooth contact and measure clearance between
coupling teeth at 90 degree intervals around coupling. Repeat three times and record readings. Backlash must not be less or greater than
design as the gear teeth could be grabbing.
D.MAIN REDUCTION GEAR MAINTENANCE
a.
All bearings used in the reduction gears are sliding surface contact
journal bearings. This type of bearing
generates a lot of heat due to friction.
Oil to the reduction gears must be at the proper quality, quantity,
temperature and pressure if it is to do its job. Cleanliness of the oil can never be over‑stressed. Lint or dirt, if left in the system, could
clog the oil spray nozzles. The lube
oil strainers can not trap very fine particles of metal and dirt and these fine
particles can become embedded in the bearing metal and cause wear on the
bearings and journals. The particles
passing through gear teeth act like a lapping compound and removes metal from
the teeth. Anytime you find any water
in the lube oil system, the cause must be found and corrected immediately. Even a small amount of water can cause
pitting and rusting and acidic attack of components.
b.
Under normal conditions, a shipyard should handle major repairs and
major items of maintenance.
Inspections, checks and minor repairs will be handled by ships
force. Onboard spares should be enough
to replace 50% of the number of reduction gear bearings. Any maintenance or replacing of reduction
gear bearings is usually accomplished by a depot level activity due to the
availability of tools, training, cost and the intense QA required. Usually bearings are interchangeable between
the port and starboard sides. All
needed tools and equipment should also be onboard in case of an emergency.
c.
Reduction gear journal bearings have what is called a pressure half and
non-pressure half. The non-pressure
half has a scribe line at one end in the center of the bearings. The pressure half has three scribed lines at
one end, one in the center, and one on either side at a 45 degree angle from
the middle. The crown thickness of each
shell is measured at these scribe marks, usually 1 1/4" from the end. The measurements are taken by the
manufacturer during initial alignment.
they are stenciled onto the bearings for future alignment checks. Bearing wear can be measured by determining
the differences in crown thickness.
Bearing wear should never be great enough to allow incorrect gear
contact.
d.
If at anytime, you have a loss of lube oil casualty and suspect possible
bearing damage, inspect the high speed journal bearings first. As these are the bearings that see the
fastest speed, if there is damage, it will probably be here.
e.
Bearing replacement is a major undertaking, and should never be
accomplished without the proper technical manual. As stated earlier, bearing replacement or repair is usually
accomplished by a depot, but in an extreme emergency ship's force might be
required to perform certain repairs. If
a bearing is replaced, ensure that bearings on the end of the gear or pinion do
no differ by more than 0.002 inch to maintain shaft parallelism. This involves very precise, controlled
actions and tools to complete safely.
f.
Once a bearing is replaced, place muslin bags in the lube oil strainers
to trap any dirt or foreign matter that is too fine to be stopped by the
strainer. Change the muslin bags every
30 minutes until they no longer pick up dirt.
At this point you can engage and start the jacking gear.
E.INSPECTION REQUIREMENTS
a.
The following inspections of reduction gears shall be made in accordance
with the preventive maintenance system:
(1)
Weekly circulate lube oil; rotate main reduction gear. This is accomplished when the main
propulsion plant has been idle 7 days.
(2)
Monthly inspect reduction gear interior. Accomplish this monthly when in idle lay-up after 30 days (yard
period/upkeep).
(3)
Semi-annually inspect reduction gear spray nozzles, inspect reduction
gears. This is also accomplished when
inspection of security devices indicates that unauthorized entry may have taken
place.
(4)
It is highly recommended that the reduction gear be inspected as a part
of your relieving POA&M. Both on
coming and off going.
F.GEAR NOMENCLATURE. These standard terms should be used in
recording material history. These terms
are found in NSTM 9420 Reduction Gears.
a.
Active profile is the entire loaded side of the tooth as it goes through
the gear mesh.
b.
Top land - the top of the tooth.
c.
Filet is the area from the bottom of the profile to the top of the root
land.
d.
Sides of gear - the end of the tooth.
e.
Root land - the bottom of the tooth.
f.
Transverse profile is the actual profile of the tooth as it goes through
the gear mesh.
g.
Tip round - the beginning of the end round.
h.
End round is the area of the tooth from the tip round to the side of the
gear.
i.
Fillet radius is the concave radius which joins the tooth profile and
the bottom of the tooth.
j..
Edge round - the rounded edge of the tooth profile.
G.POINTS OF ATTENTION DURING A REDUCTION
GEAR INSPECTION. When inspecting
reduction gears, the Engineer Officer should look for the following:
a.
Poor tooth contact pattern, heavy contact at one end which tapers off to
zero contact at less than 80% of the tooth length. Internal alignment of pinion to gears should be corrected until
tooth contact exceeds 80% of length (this is done by a shipyard). Ideal tooth contact is in the middle area of
the tooth profile, not at the top or bottom, as this can stress gear teeth and
cause damage. The maximum amount of
tooth contact is approximately 95%. If
tooth contact were 100% the tooth could be stressed at the end round and
possibly break.
b.
Pitting is the loss of surface material in the shape of small craters,
or pits, occurring close to the tooth pitch line, caused by excessive tooth
bearing pressure.
c.
Dirt tracks are caused by foreign particles passing through the gear
mesh, high spots result if the dirt track is prominent. these should be visible at the same spot on
all gears where contact occurred.
d.
Moderate scoring is the loss of surface material in the shape of radial
lines, or scores, occurring above and below the pitch line, caused by excessive
bearing pressure and/or marginal lubrication.
e.
Severe scoring is the heavy loss of surface material occurring above and
below the pitch line with radial score marking, tip will have feather edge,
caused by material plastically deformed.
f.
Wear may be defined as the removal of metal from gear teeth.
g.
Normal wear may be defined as removal of metal from gear teeth at a rate
that does not impair satisfactory operation of the gear.
h.
Cracked teeth are clearly identified by magnaflux inspection.
i.
Tooth fatigue is progressive, a short crack appears and then propagates. Characteristic "Oyster Shell" can
usually be seen.
j..
Broken tooth. A section of tooth
broken away, if a broken section is at one end and has fatigue, eye fracture
may be caused by poor contact or upset tooth.
If broken section has no noticeable fatigue eye, break may be due to
overload, sudden shock or foreign object passing through mesh, gears with
broken teeth should be replaced.
H.GEAR INSPECTION. It is recommended that the Engineer Officer
review all documentation (NSTM's, technical manuals and MRC's) before
conducting the actual inspection in accordance with the MRC. Prior to opening the gear case the following
steps must be performed to ensure a safe and controlled evolution:
a.
The Engineer Officer must be contacted for entry and his presence is
normally required when the gear case is opened.
b.
Secure the area to prevent unauthorized access.
c.
Enter in the engineering log the time, date, reason for entry and
findings. An entry must be made when
the inspection starts and when it is completed. The entry at completion must contain all results of the
inspection as an official material history.
d.
Clean the area around the inspection ports. This prevents foreign material from inadvertently entering the
gear case.
e.
Prior to opening the inspection cover, remove personal items from your
clothing and person, to include collar devices, pens, jewelry, watches and
empty pockets. Tape pockets shut.
f.
When using portable illumination devices secure a line to them to
prevent their entering the gear assembly in the event they slip from you grip.
g.
If the gear must be left open without work in progress, post a
responsible petty officer E-5 or above to ensure security.
I.DOCUMENTATION. The remarks "INSPECTION SAT OR UNSAT" entered in the
engineering log is unacceptable. It is
highly recommended that some type of formal inspection from be developed, or
use our sample, so that after the last inspection there is a detailed record of
your findings (see Figure 4).
MAIN
ENGINE REDUCTION GEAR INSPECTION RECORD
|
NOMENCLATURE OF GEAR
TOOTH |
PERCENT
AND INCHES OF WEAR |
CHANGES
SINCE LAST INSPECTION *NOTE RUST IF APP. |
|
|
2ND
REDUCTION GEAR |
|||
|
|
FWD
HELICAL |
AFT
HELICAL |
COMMENTS |
|
2ND
REDUCTION GEAR PINION: (UPPER) |
|||
|
ACTIVE PROFILE TOP LAND FILLET SIDES OF GEAR ROOT LAND TRANSVERSE PRO. NORMAL SECTION TIP ROUND END ROUND FILLET RADIUS EDGE
ROUND |
% IN % IN % IN % IN % IN % IN % IN % IN % IN % IN % IN |
% IN % IN % IN % IN % IN % IN % IN % IN % IN % IN % IN |
|
|
|
|||
|
2ND
REDUCTION GEAR PINION: (LOWER) |
|||
|
ACTIVE PROFILE TOP LAND FILLET SIDES OF GEAR ROOT LAND TRANSVERSE PRO. NORMAL SECTION TIP ROUND END ROUND FILLET RADIUS EDGE
ROUND |
% IN % IN % IN % IN % IN % IN % IN % IN % IN % IN % IN |
% IN % IN % IN % IN % IN % IN % IN % IN % IN % IN % IN |
|
|
SPRAY NOZZLES STAR.
SIDE 1. 2. 3. 4. |
% SAT/UNSAT % SAT/UNSAT % SAT/UNSAT %
SAT/UNSAT |
|
|
|
SPRAY NOZZLES PORT.
SIDE 1. 2. 3. 4. |
% SAT/UNSAT % SAT/UNSAT % SAT/UNSAT %
SAT/UNSAT |
|
|
Figure
4