INFORMATION
SHEET
TURBINE/GEAR
MAINTENANCE
Information
Sheet Number 62S-103
INTRODUCTION
The Main Engine and Reduction Gears
are two of the most simply designed pieces of equipment in the propulsion
plant. Although their design is simple,
they are two of the most important pieces of equipment on board a ship. Without the main engine and the reduction
gears a ship is unable to get underway or maneuver. The maintenance and thorough monitoring of these components are
paramount to safe and prolonged operation.
There is nothing that can be done to an operating engine and reduction
gear while operating other than to maintain the lube oil's cleanliness and to
monitor and record the various readings taken.
These readings are the key indicators used to determine what maintenance
is required and needed.
1.
Information in this student guide complements MRCs, information in NSTMs
and manufacturer's technical publications.
2.
Where PMS coverage applies, preventive maintenance will be accomplished
in accordance with MRCs. The MRC
supersedes all other procedures. It
should be noted that PMS is the minimum required, the Engineer Officer can
always demand more, but PMS is very detailed and precise throughout the fleet
on main engine maintenance.
3.
NSTMs, manufacturer's equipment manuals, ship's information books,
blueprints, and applicable documents (TYCOM maintenance manuals/instructions,
etc.) will provide detailed procedures for maintenance, inspections and tests.
4.
These publications also provide information for the evaluation of tests
and inspection not covered by MRC's.
REFERENCES
(a) Reduction
Gears Technical Manual NAVSEA 0951-LP-022-6010
(b) Propulsion
Turbines NSTM Chapter 231
(c) Propulsion
Reduction Gears, Couplings, and Associated Components NSTM Chapter 9420
INFORMATION
A.PURPOSE OF MAIN ENGINE/REDUCTION GEAR
MAINTENANCE. The maximum operational
reliability and efficiency of an engineering plant requires a planned program
of inspections, not only to discover parts that may fail at a critical time,
but to eliminate underlying conditions such as misalignment, corrosion, erosion
and improper fabrication.
1.
RESPONSIBILITY OF THE ENGINEER
OFFICER
a.
The Engineer Officer's knowledge and supervision directly affects this
program of inspections and maintenance.
He/she must insure that the proper techniques were used and that the
data derived from the inspections are properly interpreted.
b.
Engineering maintenance is the coordination of many parts; technical
knowledge, i.e. corporate knowledge and technical skills of personnel, (PMS)
and of course publications and references.
c.
Engineering planned preventive maintenance has been formalized but it
must be understood that this program is only the minimum requirement.
d.
An Engineer Officer should have an in-depth understanding of the PMS
requirements and insure supplemental maintenance is accomplished to insure
equipment reliability and safe operation.
e.
Training should also be considered as part of a proper engineering
maintenance program. The training
should not only include proper maintenance procedures but also information that
will insure that the equipment is operated under the proper procedures and
parameters.
2.
TURBINE MAINTENANCE
a.
NSTM Chapter 231 Propulsion Turbines is the "bible" for all
maintenance actions, inspection procedures and casualty control procedures for
main turbines. Taken from the NSTM is a
table showing turbine maintenance items and the purpose for each. Periodic tests and inspections have been
developed that will insure the items listed are covered (see Figure 1).
MAINTENANCE ITEMS AND PURPOSE TABLE
|
ITEM |
PURPOSE |
|
Verification of radial and axial
position of the rotor by appropriate clearance methods |
Avoid internal rubs that can make
equipment inoperable |
|
A clean lube oil system and the proper
lubricant quality and quantity |
Avoid wiping of bearings, scoring of
journals and thrust collar and chemical attack on those and other critical
surfaces |
|
Freedom of turbine controls |
Avoid slow action or hag up of
throttles |
|
Check condition of oil deflectors and
waste oil drains |
Avoid ingress of oil into steam system |
|
Check condition of water drains |
Avoid ingress of water into lubricating
systems, blade erosion and water slugging |
|
Check cleanliness of machinery
internals |
Avoid ingress of foreign material
through access openings or through connected piping, which restricts internal
damage (mechanical or chemical) |
|
Check condition of shaft and gland
packing |
Avoid blowing steam into engineroom or
pulling air into turbine or condenser |
Figure
1
PERIODIC
TESTS AND INSPECTIONS
|
TESTS/INSPECTIONS |
FREQUENCY |
|
Operate LO purifier while underway |
Daily |
|
Operate and lubricate all valve operate
linkages |
Monthly (if secured) |
|
Take micrometer readings on the journal
bearings of the main propulsion turbines |
Quarterly |
|
Lift sentinel and relief valves by hand |
Quarterly (some platforms are
semi-annual) |
|
measure main turbine thrust clearance |
Annually |
|
Inspect interior of turbine casing |
Regular overhaul or if damage is
suspected |
|
Clean, inspect, interior of turbine
casing |
Regular overhaul cycle |
|
Inspect main propulsion bearing
journals and oil deflectors measure clearances |
Annually and regular overhaul |
|
Inspect shaft packing and journal for
condition, check clearances |
Regular overhaul cycle |
|
Foundation bolt tightness |
Regular overhaul |
|
Drain and refill operating control gear
boxes |
Annually and regular overhaul |
|
Remove and clean main steam strainer |
Regular overhaul |
|
Measure nozzle clearance |
Regular overhaul |
|
Test high and low pressure turbine
sentinel valves |
Annually or regular overhaul |
Figure
2
a.
The next table (see Figure 2) lists periodic tests and inspections for a
turbine. This is a sampling of items
and all of these items are covered under the PMS system.
b. Propulsion
Turbines are basically designed machines.
The dynamic loading and transient conditions applied to main turbines
make the inspections and maintenance vital to safe and prolonged operation. The main engine is always in operation while
underway, unless a casualty occurs. The
only time preventive maintenance can be completed is inport, with the engine
secured. Through proper scheduling, a
majority of the required maintenance can be accomplished at the same time. This should give the Engineer Officer and
MPA a "warm fuzzy", as they will be aware of the exact status of the
main engines, including all of the measurements and clearances. This information can be vital to the
Engineer Officer if a casualty occurs.
c.
The Engineer Officer will find very few actions that ship's force can do
to a main turbine. The review of
operating logs and the maintenance of clean lube oil are the best things for
the turbine. The actual inspection of
the turbine internals and casing is performed by the Engineer Officer using the
MRC. Prior to the inspection, the
Engineer Officer needs to review the MRC and NSTM 231. These documents aid the Engineer Officer in
the inspection and assists in the recording of the material history by using
standardized terms.
d.
During the inspection, the Engineer Officer is only able to see about
10-25% of the HP turbine internals and 40-60% of the LP turbine internals (see
Figure 3 as a guide). Access ports
allow viewing of the 1st stage area, the exhaust end of the HP and a view of the
balance weights. The access ports at
the steam inlet or first stage are very small and provide a limited amount of
area to be seen. This is due to the
casing halves being together and the turbine internals obstructing some of the
view. A borescope can be useful in this
area, if one is available. The access
ports on the LP turbine are considerably larger and provide a more extensive
look inside. The major areas that can
be observed are the astern elements, the exhaust of the LP and astern elements
and the diaphragms and supports.
TURBINE
INSPECTION GUIDE
|
TURBINE
PART |
LOOK FOR THE FOLLOWING |
|
Interior
surface of casing |
Corrosion,
erosion, condition of casing steam seal surfaces |
|
Nozzle
diaphragms |
Erosion/corrosion
of horizontal parting and vertical steam seal surfaces, condition of
radial/axial crush pins.
Erosion/corrosion pitting and cracking of vanes |
|
Diaphragm
and gland packing rings (carbon and labyrinths) |
Wear,
freedom of movement, condition of springs, position relative to the rotor |
|
Rotor
blading and shrouding |
Cracks,
dents, tears, erosion, corrosion, lifting of the shroud, integrity of
stellite shields, axial and radial rubs |
|
Rotor |
Surface
cracks of chromed or spray metalled areas.
Balance weights intact and firmly anchored. Erosion/corrosion of packing areas and integrity of end plugs
on hollow rotors. Journal
condition (scoring, wear, pitting) Thrust collar (scoring, wear, pitting, tightness) |
|
Journal
Bearing |
Wear,
loose babbitt, contact pattern, scoring, tin oxide, RTE intact |
|
Thrust
Bearing |
Shoe
wear, loose babbitt, contact pattern, scoring, wear of leveling plate
supports, RTE intact |
|
Blading
radial seals |
Wear,
pieces broken out, firmly seated |
|
Horizontal
joint (main and nozzle chest) |
Steam
cutting, evidence of leaks |
|
Casing
structure |
Cracks
in casing, particularly in the HP first stage shell area and floor of main
steam chest. Cracks in casing support
plates, welds, flex, plates. Proper
clearance for and freedom of keys and sliding feet. Distortion of gland housing. |
|
Valves
(nozzle, bypass transfer, extraction and drain) |
Scoring
of lift rods in way of bushings.
Condition of stems that may indicate leakage or hang up. Wear of linkages, bearings and cams |
|
Rotor
position differential expansion indicators |
Wear,
adjustment, calibration |
|
Nozzle
blocks |
Cracks
in ligaments between reamed nozzles.
Both retainer plates out of position.
Loose or broken bolts |
Figure
3
a.
Three things can be useful to the Engineer Officer during a turbine
inspection: the use of Morpholine or a
corrosion inhibitor when operating; reviewing of the operating logs and
knowledge of where damage is most probable.
Morpholine or some corrosion inhibitor is carried over in the steam
supplied by the boiler. This
"coats" the piping and equipment internals. These components become either a light gray or brownish in
appearance. The Engineer Officer should
be looking for a difference in color.
Cracking, erosion or corrosion affect this protective layer and the
color will appear different. The
Engineer Officer should be keying in on this, as it is hard enough to see the
turbine internals. He or she should be
aware of this fact and how it will help them.
Also, the use of corrosion inhibitors has greatly reduced the problems
encountered by corroding materials and this problem is almost non-existent now.
b.
The review of operating logs against design limits provided in the main
engine technical manuals can help identify possible steam flow problems. Abnormal pressures and temperatures can be
used to highlight suspected problem areas.
If journal bearing clearances are satisfactory, there should be no
problems in the turbine's steam flow.
The flow design of the turbine is dependent on the alignment provided by
the bearings.
c.
The probability of damage or wear is greatest where the highest
pressures and temperatures occur. This
area is easy to find; the HP first stage and nozzle block (the small access
ports allow viewing this area) and the astern elements of the LP turbine (large
access ports show this). If there is no
damage in these areas, it is a safe bet that the rest of the turbine is okay
(as each stage of the turbine there is a pressure drop and temperature is
decreased). This area should be of
primary interest to the inspector.
d.
Important considerations behind the requirements for turbine PMS are
maintaining the design steam path clearances and insuring proper axial and
radial clearances. As stated earlier,
operating logs can be very useful at this point. The two components used to maintain alignment are thrust bearings
and journal bearings.
e.
Axial clearances are designed to allow for turbine rotor/casing
expansion, contraction, and movement.
This movement is limited by use of a Kingsbury type thrust bearing on most
platforms. Axial clearances can be
checked both during operation and when the turbine is idle by using the rotor
position indicator. This reading
provides a "quick look" or reference of axial alignment.
f.
Radial position and alignment of a turbine is maintained by the use of
journal bearings. Excessive wear or
damage to journal bearings can cause extensive problems inside a turbine, much
more than average problems experienced by a damaged thrust bearing. The thrust bearing's maximum clearance is
only half the distance between the casing and blading, this allows some safety
margin. Once the journal bearing is
damaged, the shaft "drops" and rests on the internal components
(gland seal and diaphragm labyrinths).
This damage affects the seals and steam flow through the turbine. Watchstanders might find this by their
hourly readings. If you notice an
increase in gland seal steam, blow by of steam from the glands or slightly
abnormal bearing temperatures, you should investigate. It is important to realize, that once the
internal labyrinths are damaged there is generally little you can do. The ship's force, on most platforms can only
change out or repair the outer set of labyrinths, because the turbine casing
allows no access to the others.
Maintaining the radial position of the turbine and reduction gear
components within design limits prevents damage to:
(1)
Turbine casing
(2)
Turbine blading and shrouding
(3)
Turbine diaphragm and packing rings
(4)
Turbine oil deflector rings
(5)
Reduction gears due to mis-alignment
g..
Propulsion turbines are balanced to a "T" prior to assembly in
a ship. As long as all operating
parameters are within specifications, the turbine will last for a long
time. If something goes wrong with a
turbine, sight and hearing will probably be the first indication of something
wrong. Your watchstander is the first
line of defense. Does he or she know
this?
h.
The way a turbine is operated can affect the maintenance and reliability
of the turbine. A rotor should never
sit still for more than 5 minutes after steam has been admitted. If a turbine in operation should suddenly
vibrate, the problem could be any one of the following:
(1)
Water in the turbine
(2)
Bearing failure
(3)
Bent or broken propeller blades
(4)
Unbalance due to broken or missing rotor blades
(5)
Rubbing of blading labyrinth packing or seal rings
(6)
Bowed rotor
i.
If you hear a rumbling sound and the turbine begins to vibrate, it is
probably water or foreign material. But
it is important to know that vibrations or noises from either the turbine or
shaft can travel to the reduction gears.
This greatly affects the watchstanders in their troubleshooting.
j.
Sometimes the Engineer Officer might feel an internal inspection is
needed if the noises or vibrations were excessive (prolonged operation while
bowed or with an excessive vibration can be a contributing factor). A sure sign of something rubbing on the
rotor will be a shiny spot on the rotor (that difference in color again). If this is noted during an inspection,
immediately investigate the cause and correct it.
k.
When rubbing of a turbine blade or labyrinth occurs, the cause will
probably be a bowed rotor. Other causes
could be:
(1)
A defective thrust bearing (usually noticed in an RPI reading)
(2)
A wiped journal bearing (possible problems with gland seal steam)
(3)
Foreign material inside the casing (Equipment close-out sat?)
(4)
Differential in the amount of expansion between the casing and the rotor (proper warm up of the
turbines can prevent this)
l.
A lot of these problems are preventable by operating safely in
accordance with EOSS. The satisfactory
operation of a turbine depends largely upon the axial and radial alignment of
the rotor in the casing. During normal
operations, the temperature of the oil leaving the bearing is the sole
criterion available to the operator for judging the conditions of the various
bearings. Oil temperature leaving a
bearing will vary depending on the changes in speed, especially since all
turbine and reduction gears are sliding surface contact bearings. These bearings develop a lot of heat due to
friction and are dependent upon proper quantity and quality of the
lubricant. Thus, keeping the lube oil
quality at it's best is vital to prolonged operation. Over a period of time you should be able to chart the changes and
detect any bearing that may be out of specifications (reviewing of operational
logs again).
m.
If it is suspected that one of the bearings is out of specifications,
when the turbine is secured you can take a "quick look" at the
bearings. A depth gage is the quickest
and easiest means to determine the amount of wear on a journal bearing. When a bearing is first installed, make a
measurement on the bearing to act as a base point. Log this reading. This is
your reference point. Never make
repairs to a bearing solely upon the outcome of a depth gage reading. If a depth gage reading shows up bad, then
make other measurements to the bearing before trying to make repairs.
n.
If other measurements are required besides a depth gage, then the
bearing will need disassembly and inspection.
Some journal to bearing rubbing contact is made on each start. A good bearing will show a polished area
centered in the lower half of the bearing.
Discoloration of bearing surfaces almost always indicate a lubrication
problem. Moisture in the oil and
operation under high temperatures can produce a tin oxide coating on the
bearing. This coating is very hard and
builds up to reduce bearing clearance.
o.
If a bearing is to be replaced, ensure the spare meets all the design
specifications prior to reassembly.
When removing an old bearing, do not lift the rotor more than .005 inch. Lifting the rotor too much will damage the
shaft packing. The new bearing must be
reassembled properly. You can put a
bearing in backwards. This could lead
to another casualty due to lack of lubrication.
p.
The easiest way to measure the axial clearance is by the installed Rotor
Position Indicator. Another means would
be to position a dial indicator against the rotor and jack the rotor fore and
aft three times, using the average of the three. If there is an indication of a worn thrust bearing, then remove
the cover to the bearing and make a feeler gage measurement of the bearing. If a bearing needs to be repaired, then
repair all surfaces, make new measurements and shim the bearing to ensure it
meets all specifications on oil clearances.
q.
Most inspections of the turbine internals will be done through access
covers. there are two times when you
would remove the turbine casing. The
first is when there is knowledge or suspicion of internal damage. In this case you should get technical
determination of the necessity to disassemble from NAVSEA. NAVSEA will review your operating logs, take
their own readings to discover what is going on with the turbine and its'
internals. The second time would be
three months prior to overhaul and then NAVSEA will again repeat the process to
see if lifting the casing is absolutely necessary. Submit a report to the type commander about the condition of the
turbine. In both situations the type
commander should be aware of the condition of the turbine and will make the
final authorization, after he has all the information, to lift the
casings. If it is not absolutely
necessary, an alternate maintenance action will take place due to the cost of
lifting the turbine casing.
r.
Whenever there has been a main propulsion turbine opened for repair or
inspections, the work is not complete until a dock trial and post repair trial
has been satisfactorily completed. The
Engineer Officer of each ship will issue instructions for operating the plant
during a dock or post repair trial.
s.
The trial will go something like this.
Install muslin bags in the lube oil strainers and determine the
frequency to which these are to be changed.
Once the muslin bags are found to be clean, then engage the jacking
gear. Station personnel around the
turbine to detect any unusual conditions or noises. If none exist, then consider the turbine ready to do a dock
trial.
t.
For the dock trial the Commanding Officer will determine the maximum
number of RPM's he/she wants the shaft to go.
The Engineer Officer determines the amount of time needed to warm up the
main engines and when ready, notifies the OOD.
The bridge determines the number of RPM's and slowly increases to the
maximum RPM allowed. If there are no
difficulties, then the turbine would be ready for a post repair trial.
B.MEASUREMENT METHODS FOR TURBINE/GEAR
BEARINGS
a.
Journal bearings can be measured in a few ways. these are the ways available to determine
bearing clearances:
(1)
The Depth Micrometer Method.
This is the quickest method to get an indication of ring wear. These is no disassembly of the bearing. The turbine must be isolated and secured
from rotating and the lube oil system must be secured for at least 24 hours
prior to taking the measurement.
NOTE: This method is only a
quick check and should not be used as a final method of determining bearing clearances.
(2)
The Bridge Gage Method. This
method requires the component to be placed out of commission and
disassembled. It is used when there is no
access for a micrometer in the bearing.
This requires two personnel to perform and is not as accurate. Only a few ships use as the method for
taking measurements.
(3)
The Crown Thickness Method. This
method requires disassembly of the journal bearing. The bearing is rolled out of the component and a micrometer is
used to take readings of the bearing thickness at scribed lines on the side of
the bearing shell. A drill bit or round
object is needed also. The micrometer
has a square face and the bearing shell has a rounded shape, the drill bit
allows the measurement to take place.
(4)
The Leadwire/Plasti-gage Method.
This method requires the component to be placed out of commission and disassembled. Leadwire/Plasti-gage method is used
primarily on spring bearings which do not have a bridge gage assembly or access
hole for a depth micrometer and because of the size and location of the spring
bearings.
(5)
The OD and ID Method. The
bearing is disassembled and the inside of the bearing is measured. The outside of the shaft is measured. The clearance is the difference between the
two. This method is very accurate,
allowing the bearings wear pattern to be checked. It is recommended to go from a depth micrometer reading to this
method as final verification of readings.
b.